Clarkson GO Station - North Platform Improvements

 

 

Company
KENAIDAN GROUP
Facility Type
Railways/Airports
Location
1110 Southdown Road, Mississauga
Start Date
01/2008
End Date
03/2010

 

 

PROJECT DESCRIPTION

The contract included: north platform improvements which accommodated a track that was installed by CN in July 2009.
The contract included: inverted T-curbs; hydronic snow melt system and asphalt; shoring with H-piles and lagging; new east and centre stair structures both with 2 stairs sets and cast-in-place tunnels; 2 elevators; mini platform and canopy; and new boiler, electrical and communications building. A jack-and-bore tunnel system was required for the glycol piping and communication cables underneath the tracks. Kenaidan self-performed all concrete work which consisted of 2,225m² of formwork, and 576m³ of concrete. 

 

 

 

 