Wisconsin Southern Rail Bridge Rehabilitation

 

 

Company
KRAEMER NORTH AMERICA
Facility Type
Roads/Tunnels/Bridges
Location
Sheboygan County, WI
Start Date
03/2015
End Date
08/2015

 

 

PROJECT DESCRIPTION

Kraemer is rehabilitating three WSOR structures (Bridges 824, 826, and 841) over the Sheboygan and Mullet Rivers near Sheboygan Falls, WI and Plymouth, WI. Work includes full removal of the existing timber trestle at the Plymouth location, construction of two new CIP pier caps founded on 36-inch diameter caissons and two new precast abutments founded on piling. The new structure will be three-span steel beam bridge with a new timber tie deck and walkway. Steel bridge rehab work over the Sheboygan River includes removal and replacement of existing bottom cover plates, stringer replacement, gusset and stiffener remove and replace, and remove-clean-replace existing bearings.

 

 

 

 