MN-DNR Coon Rapids Dam Rehabilitation

 

 

Company
KRAEMER NORTH AMERICA
Facility Type
Dams/Power Plants
Location
Coon Rapids, MN
Start Date
End Date

 

 

PROJECT DESCRIPTION

This dam rehabilitation project included the replacement of a complete gate system, spillway, and downstream apron located on the Mississippi River. In addition, the project included 30,000 square feet of sheet piling required for cofferdam construction and 8,000 lineal feet of piling foundations. Construction of this two year project begin in 2013 with the installation of five new water control gates and construction of a new stilling basin. This work was completed before the high spring river flows in 2014.

 

 

 

 